Further to our post about the “balanced budget” for 26/27, November 2026 has seen the publication of the latest Revenue Monitoring summary and commentary, as an appendix to the Council Reports pack.

Income and Expenditure

As we anticipated, many of the projected improvements in income or reductions in expenditure have failed to materialise. This has resulted in a £9.062M variance (overspend) compared with budget. Reserves and contingency have been used to mitigate this, leading to a reported variance of £3.725M projected for the financial year.

While it may be legitimate to release the £2.68M of budgeted contingency and £2.657M of income risk reserve it illustrates that the Council Budget is still not under control and continues to build a negative legacy for subsequent administrations and ultimately council tax payers.

The fall in income revenue may reflect the continuing disruption in City Centre accessibility due to cycle works and refurbishments, with visitor numbers to the Roman Baths 5% down, representing £1M in lost income.

Bizarrely for a Tourist City, there is no Tourist Office and very little external promotion, especially among Social Media platforms.

The City is also unable to fill its Commercial properties with projected revenues down £872K on un-let South Quays properties, perhaps reflecting that Bath is not an attractive destination for businesses, especially start-ups and high-growth enterprises.

Similarly, the £7M overspend on Children’s services results from the use of agency staff. Again, attracting suitable candidates to fill numerous staff vacancies reflects the unattractiveness of working for the Council, and the lack of effective leadership in this area.

Capital programme

Capital programme delivery also continues to suffer delays, overspends and re-phasing. No reporting of cost to completion is included, indicating a lack of financial and delivery control.

Some examples:

Somer Valley Enterprise Scheme, shows a variance of £4.251M that should have been spent in this FY but is now pushed back to next FY.

Guildhall Roof refurbishment – estimates are higher than budgeted, the scheme has been postponed until June 2027 and will cost more than the budgeted £3.014M.

Englishcombe Lane Supported Housing – continued delays mean the build programme will not start until next financial year.

The Social Rent programme has also been delayed, leading to a £2.181M postponed spending to future years.

Under-estimate problems have also been identified at Haycombe Crematorium to replace the Cremator, Parks improvement programmes for Hedgemead, Scholars Way, Commercial estate Fire Safety Works and Bath Quays North.

The total capital underspend for the year exceeds £12M. Underspends in this context represent programme delays, overspends and under-estimates, rather than efficient management, and continue to cause concern that there is a lack of professional leadership and control.

Also of concern is the number of projects that come in on exact budget. This indicates that expenditure takes place regardless of need – if that’s the budget, that’s what we pay. So there is no incentive for efficiency or cost-savings.

Debt

Debt for the year continues to balloon, standing at £294M in September, compared with £229M in 2025

Overall and as previously predicted, lack of Budget control has led to a deteriorating financial position for the authority.